Alabaster Repaving Project | Fall 2019

Below is a table with target dates for each of the roads listed.  We will work hard to update this site ASAP when there are changes and status updates.  Weather and road conditions could impact the schedule, please check back here for updates.

All locations will be posted to notify traffic several days prior to work and will be adjusted as needed.

Area Specific Road Date Scheduled Status
Fox Valley Fox Valley Drive 9-9-19 thru 9-11-19 Complete
  Fox Valley Highland Drive 9-9-19 thru 9-11-19 Complete
  Fox Valley Highland Circle 9-9-19 thru 9-11-19 Complete
Lacey Grove Lacey Avenue 9-20-19 thru 9-22-19 In Progress
  Crider Road 9-20-19 thru 9-22-19 In Progress
Lake Forest / The Cove Red Bay Drive 9-23-19 thru 9-25-19  
  Red Bay Trail 9-23-19 thru 9-25-19  
  Red Bay Cove 9-23-19 thru 9-25-19  
  Scenic Lake Drive 9-23-19 thru 9-25-19  
  Scenic Lake Cove 9-23-19 thru 9-25-19  
Scottsdale Heather Lane 9-25-19 thru 9-27-19  
  Mitch Lane 9-25-19 thru 9-27-19  
Mountain Lake Mountain Lake Drive 9-30-19 thru 10-1-19  
  Mountain Lake Trail 9-30-19 thru 10-1-19  
Wisteria Wisteria Drive 10-2-19 thru 10-4-19  
  Wisteria Lane 10-2-19 thru 10-4-19  
Sugar Hill Area Sugar Hill Lane 10-7-19  
Limestone Park Limestone Park Drive 10-8-19